An undergraduate research project is exploring how renewable energy could provide reliable and sustainable power to a rural community in Western Uganda, which remains without electricity despite being within five kilometres of the national grid.

The project, presented by Electrical and Electronics Engineering student Yakub Bwengye Namara during a Brown Bag session organised by the Research and Innovation Department on August 27, 2026, focuses on Muziira 1 Village in Bushenyi District.

The village has about 200 households, 30 businesses and seven community institutions, including schools, churches and clinics. Residents rely heavily on biomass for cooking, while the lack of reliable electricity affects households, businesses and institutions with different energy needs.

The project seeks to establish how much electrical and thermal energy the community requires, what renewable resources are available locally and what type of system could meet those needs reliably and affordably.

“This project proposes a techno-economic feasibility assessment for a decentralised hybrid renewable energy system in Muziira 1,” Namara says.

The research is assessing the energy requirements of different users. Households need electricity for lighting, phone charging, radio and television, while businesses such as shops, salons and milling enterprises have additional requirements for machinery, refrigeration and longer operating hours. Schools and clinics have other needs, including evening lighting and refrigeration.

The project is also assessing solar energy and locally available biomass resources, including cattle manure and coffee husks, which could potentially be used for biogas and briquette production. Solar data from the Global Solar Atlas indicates irradiation of about 1,835 kWh per square metre per year.

Namara’s fieldwork involves collecting information from households, businesses and community institutions to develop realistic energy-use patterns, with particular attention to evening demand and the times when businesses use energy for productive activities.

The collected data will then be used to assess a proposed Solar PV–Battery–Biogas hybrid system alongside other possible energy configurations.

“The study addresses a critical data gap by quantifying local electrical and thermal energy demand alongside renewable resource availability,” Namara says.

Preliminary comparisons indicate a trade-off between installation cost and reliability. Extending the electricity grid has an estimated investment cost of about $505 (KSH65,367) per customer, compared with $1,175 (KSH152,093) for a solar microgrid. However, the solar microgrid has an estimated reliability of 98.7 per cent, compared with less than 90 per cent for grid extension.

The project aims to identify the most appropriate energy system for the village by considering both cost and reliability, rather than focusing only on the initial cost of installation.

Its eventual feasibility assessment will bring together the community’s energy-use patterns, renewable resource availability, system costs and performance, as well as potential environmental and social benefits.

The project illustrates how undergraduate research can be applied to practical challenges facing communities. By starting with the energy needs and resources of a specific rural village, it seeks to provide evidence that could inform future decisions on decentralised energy solutions in underserved communities.